Before works could begin, the resident badgers had to be safely relocated. A one-way badger gate system was installed months in advance, allowing the animals to leave the site without returning.
Once the site was clear, WTL identified active setts and stabilised the ground using cement grouting. A total of 71m³ of grout was pumped into the embankment with support from a local supplier who provided the grout pan and mixer.
To prevent future burrowing and slips, hex wire netting was rolled out from the crest to the trackside and secured with 500mm high-tensile U-shaped pins. Over 8,500m² of netting was installed. Using Spanex guns, the netting was locked tightly in place to provide continuous coverage.
The works, originally scheduled for 12 weeks, were completed in just 9. By finishing early, WTL helped the client reduce on-site costs while also safeguarding the embankment against future risks of badger activity and instability.
We'll discuss all of your options