Protecting the Line at Victory Pewsey

WTL were commissioned by Construction Marine Ltd to deliver badger mitigation works on the Western Region. The project combined environmental protection with embankment stabilisation to ensure the railway remained safe and operational.

Preparation

Before works could begin, the resident badgers had to be safely relocated. A one-way badger gate system was installed months in advance, allowing the animals to leave the site without returning.

Our Approach

Once the site was clear, WTL identified active setts and stabilised the ground using cement grouting. A total of 71m³ of grout was pumped into the embankment with support from a local supplier who provided the grout pan and mixer.

To prevent future burrowing and slips, hex wire netting was rolled out from the crest to the trackside and secured with 500mm high-tensile U-shaped pins. Over 8,500m² of netting was installed. Using Spanex guns, the netting was locked tightly in place to provide continuous coverage.

Outcome

The works, originally scheduled for 12 weeks, were completed in just 9. By finishing early, WTL helped the client reduce on-site costs while also safeguarding the embankment against future risks of badger activity and instability.

Civils

Geo-tech

Plant

Arboriculture

Fencing

Access

Request a callback